Client: Alwatania For Industries
Contract Duration: 24/04/2013 To 20/02/2015
The Project is Located in the Industrial Area, Durma’a, the Owing Entity is (Al Watania for Industrial Co.) on the total Area of 125,000 M⊃2;, and it was Executed according to the Specifications & Drawings. The detailed illustration (Al Watania for Industrial Project) Works, Etraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities, construction of the “main dryer Building “
Client: Saudi Ceramics Company
Contract Duration: 3/03/2014 To 3/05/2015
The Project is Located in the Industrial Area, Durma’a, the Owing Entity is (Saudi Ceramics Co.) on the total Area of 125,000 M⊃2;, and it was Executed according to the Specifications & Drawings. The detailed illustration (Saudi Ceramics Project) Works, Etraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities, construction of the “main dryer Building “and the installation the Excavator Cart Rail way.
Client: MODON
Contract Duration: 21/05/2015 To 20/02/2016
The Project is Located in the second Industrial Area in Riyadh, the Owing Entity is (Saudi industrial property authority “MODON”) on the total Area of 7,200 M⊃2;, and it was Executed according to the Specifications &Drawings. The detailed illustration this Project Works, Extraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities.
Client: MODON
Contract Duration: 20/05/2015 To 21/02/2016
The Project is Located in the third Industrial Area in Riyadh, the Owing Entity is (Saudi industrial property authority “MODON”) on the total Area of 18,000 M⊃2;, and it was Executed according to the Specifications & Drawings. The detailed illustration this Project Works, Extraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities
Client: MODON
Contract Duration: 05/01/2017 To 12/07/2019
The Project is Located in Area in Medina, the Owing Entity is (Saudi industrial property authority “MODON”) on the total Area of 28,800 M⊃2;, and it was Executed according to the Specifications & Drawings. The detailed illustration this Project Works, Extraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities
Client: National Water Company
Contract Duration: 01/12/2016 To 31/05/2018
Execution of underground water networks with 100 mm and 150 mm of ductile iron material pipes, the nominal pressure of the water networks (16 Bar) , including excavation and backfilling , and all the connection accessories and fittings and the supply and installation of the network gate valves diameter 100 & 200 mm ,, And the asphalt work and all road recovery works and all what is needed to finish the works in the ideal manner.
Execution of water networks and Miscellaneous water lines in the district of (Namar) Riyadh (Phase 1
Client: National Water Company
Contract Duration: 01/12/2016 To 31/05/2018
Execution of underground water networks with 100 mm and 150 mm of ductile iron material pipes, the nominal pressure of the water networks (16 Bar) , including excavation and backfilling , and all the connection accessories and fittings and the supply and installation of the network gate valves diameter 100 & 200 mm ,, And the asphalt work and all road recovery works and all what is needed to finish the works in the ideal manner.
Execution of water networks and Miscellaneous water lines in (Heteen - Malaqa - Al Nakheel - Al Aqee
Client: National Water Company
Contract Duration: 12/06/2017 To 11/02/2018
Execution of underground water networks with 100 mm and 150 mm of ductile iron material pipes, the nominal pressure of the water networks (16 Bar) , including excavation and backfilling , and all the connection accessories and fittings and the supply and installation of the network gate valves diameter 100 & 200 mm ,, And the asphalt work and all road recovery works and all what is needed to finish the works in the ideal manner.
Client: MODON
Contract Duration: 12/02/2017 To 01/09/2018
The rehabilitation of the safety requirements for the ready factories in ( Riyadh-Al Kharj-Souder-Az Zulfi- Qassim-Shaqra) including the execution of Polyurethane foam layer of insulation for the factories roof top with the acrylic protection layer & the replacement of the Aluminum glass conventional doors with fire rated emergency doors according to the specifications , Also the scope of works includes the installation and replacement of the emergency lighting system members according to the specifications , and the rehabilitation and maintenance of the fire alarm systems installed in the factories .
Client: MODON
Contract Duration: 29/10/2018 To 28/06/2019
The rehabilitation of the safety requirements for the ready factories in ( Riyadh-Al Kharj-Souder-Az Zulfi- Qassim-Shaqra) including the execution of Polyurethane foam layer of insulation for the factories roof top with the acrylic protection layer & the replacement of the Aluminum glass conventional doors with fire rated emergency doors according to the specifications , Also the scope of works includes the installation and replacement of the emergency lighting system members according to the specifications , and the rehabilitation and maintenance of the fire alarm systems installed in the factories .
Client: MODON
Contract Duration: 04/09/2019 To 03/02/2022
The Project is Located in Area in Madina, the Owing Entity is (Saudi industrial property authority “MODON”) on the total Area of 7,200 M⊃2;, and it was Executed according to the Specifications & Drawings. The detailed illustration this Project Works, Etraction of Steel Structural, Construction of underground water tank, installation of the production infrastructural & production facilities
Client: MODON
Contract Duration: 04/09/2019 To 03/09/2020
The project is located in the Madinah Industrial City, Al Madinah, Saudi Arabia. The scope of work of the proposed project includes the street lighting network, wet utilities network, open channels with riprap and asphalt roads with highway signs. The contracted project duration is 12 months from the site handover date.